There is a setting in the control file which will need to be changed to do this.
β
Once in the control file do the following:
Search for DC_SCRAP_COVER
Set the flag to have one of the following settings:
Create New - This will create a new works order to cover the replacement quantity
Up W/O Qty - Once the 3 are scrapped and the works order reduced to 97, the replacement will be added back to the works order, bringing it up to 100 again
Ask Up + New - Will ask the user if they want to do option a or option b
Ask All Options - Will ask the customer if they want do option a, option b or nothing
Nothing - The works order will stay at 97
If you have the issue described your current setting is likely option e. Please choose which other option best suits the needs of your business.