Resources overwritten incorrectly after import from Orchestrate

We have discovered Works Orders where resources have changed names automatically . They came up as resource no longer on file on the Works Order, but on FactoryMaster they have different resource names.

B
Written by Bogdan Branetiu
Updated this week

When you import into Orchestrate, it will schedule the job on any resource in the same resource group. As you are then importing the schedule back into FactoryMaster, this is why the relevant resources are showing in the sky blue colour.
​
You can also change these to locked/unlocked as you need to at the route level in Manufacturing Route Maintenance. Once you change them here it will give you the option to update the pending works orders that use that route.