Skip to main content

FactoryMaster: Set how many items need to be worked on to make one finished item on the route

We are expecting to make 500 items but the planned quantity is 100000.

S
Written by Sebastian Pavel Rus
Updated this week

To change how many items are need to make one part, please do the following:

  1. Click Production

  2. Click Works Order Enquiry

  3. Locate your Works Order

  4. Press F5 on the Works Order number

  5. In the Operations tab press F5 on the OP Time field

  6. In the How many items are needed to be worked at THIS operation to make ONE of the finished item? field you can enter how many parts create one item

Did this answer your question?