How do I recalculate job costings for works orders?

J
Written by Jes Foxall-Beckley
Updated over 2 weeks ago

To recalculate job costings, please complete the following steps:

  1. Go to Analysis Menu

  2. Then Job Costings Details

  3. A box a pop up 'Update job costing'

  4. Click No

  5. The 'job costing details menu' will now pop up.

  6. Press Enter

  7. Select the relevant Works order(s).

  8. Press F8 to recalculate a single works order or Shift + F8 to recalculate multiple works orders.

  9. A warning message will pop up letting you know you are recalculating all works orders in question.

  10. Click Yes