Job costing will only detect items that have a job (works order) to create them. A way you can do this with BI parts that you do not need to create full works orders for is to create a 'Costing Only' works order.
On the Projects Maintenance screen, go to the Works Order tab
Click Create Costing Works Order
Choose the part number, either by using F5 or by typing manually
Make a note of the works order created, you will now need to create a Manual Job Costing Entry. See below if you need help doing this
Go to the Analysis Menu
Choose Manual Job Costing Entry
FIll in the following details, the key ones being highlighted in bold
Transaction type (RM, BI, MA etc.)
Works Order Number (Should be the number from step 4)
Supplier Code
Purchase Reference
Date Received
Date Issued
Quantity Issued
Unit Cost
Description/Notes
Click OK
Go back into project maintenance and choose your project. Now you will see the Costing will appear on the Job Cost tab