Skip to main content

Planned Costs for Sub-Level parts are not appearing in Job Costing

My planned costs in Job Costing is zero for one works order, why is this?

Written by Jes
Updated over 3 months ago

If your Planned Costs for Manufactured Parts are displaying as Β£0.00 it is possible that no Standard Cost has been set up for them. It is also possible that the MA Parts were added to the Works Order before a Standard Cost was allocated to them.

Did this answer your question?