Current Operation on Works Orders is showing as the first OP despite the order being completed

We have completed a Works Order and the Current Operation column says OP 10 when the last OP is 50, why is this happening?

J
Written by Jes Foxall-Beckley
Updated over 3 weeks ago

It is possible for the Current Operation to show a different OP to the last OP on the route. If you were to log onto the first OP for a Rework for example, this will show OP 10 in the Current Operation column.