Current Operation on Works Orders is showing as the first OP despite the order being completed

We have completed a Works Order and the Current Operation column says OP 10 when the last OP is 50, why is this happening?

Written by Jes

It is possible for the Current Operation to show a different OP to the last OP on the route. If you were to log onto the first OP for a Rework for example, this will show OP 10 in the Current Operation column.