Skip to main content

When logging into multiple works orders, the time worked should not be split equally

When I log onto multiple work orders, the time worked is split equally between all three of them.

B
Written by Booghy
Updated over 3 weeks ago

Find the relevant resource used to fulfil the works order from the routing and then complete the following steps:

  1. Select production

  2. Resource maintenance

  3. Select the relevant labour resource

  4. Click into the Resource Rate Per Hour field

  5. Change the actual labour time to: Always book the full data capture clocked time to the operation

  6. Click OK

Did this answer your question?