When logging into multiple works orders, the time worked should not be split equally

When I log onto multiple work orders, the time worked is split equally between all three of them.

Written by Arthur Ashdown

Find the relevant resource used to fulfil the works order from the routing and then complete the following steps:

  1. Select production

  2. Resource maintenance

  3. Select the relevant labour resource

  4. Click into the Resource Rate Per Hour field

  5. Change the actual labour time to: Always book the full data capture clocked time to the operation

  6. Click OK