This article can provide you with advice on this matter, if you find that the part request has doubled on the create job in Service Manager

T
Written by Tyler Martin
Updated today

Overview

If you have created a job in Service Manager, and the part request has doubled into FactoryMaster, works order is completed and feeds back to service manager, with auto-notification. Please look at the advice below, which should be helpful.


What has caused this, and how does it work?

The quantity appears as if it could been updated manually by a blank user. You don't need a special Transaction Broker installation to import records via the transaction broker. It is entirely possible to queue up import records in the transaction broker without a machine running the broker to process them, and then log in as a broker user, which would then process the queued records.


Why has this happened?​

The First quantity change, from 0 to 1, is created via the transaction broker request as the date & times are within the process start & end of the broker request.
​
The second quantity change, from 1 to 2, has been increased manually via someone logging into FactoryMaster and altering the order directly.
​
There are no subsequent broker requests for further alterations, and the second quantity change is outside of the process start & end time of the previous broker request.