When a Works Order is updated from the Route all 'non-started' operations are deleted and re-added from the Route. The system is unable to ensure that the times and resource codes will be the same so it has to remove the operations from the schedule therefore this is working by design.
Updating Manufacturing Route Instructions removes Scheduled Start and End times on a Operation
After applying a Schedule imported from Orchestrate, when i update the Manufacturing Route Instruction of a MA part, the scheduled start and finish times get removed, why is this?
J
Written by Jes Foxall-Beckley