The Production Calendar is a Non-Chargeable module within FactoryMaster, if you would like to have this module enabled within your system please raise a new case online and reference the title of this article.
To set up the Production Calendar please do the following:
Click Options
Click System Maintenance
Click System Settings
Click General System Settings
Click System Calendars
Click Production Calendar
Once in the Production Calendars you will be able to click the Change Working Week button. This will allow you to set which days production takes place on, once you have set up your working week click OK.