Skip to main content

Setting up the Production Calendars

I need to change the working week within FactoryMaster, how can i do this?

Written by Jes

The Production Calendar is a Non-Chargeable module within FactoryMaster, if you would like to have this module enabled within your system please raise a new case online and reference the title of this article.
​
To set up the Production Calendar please do the following:

  1. Click Options

  2. Click System Maintenance

  3. Click System Settings

  4. Click General System Settings

  5. Click System Calendars

  6. Click Production Calendar

  7. Once in the Production Calendars you will be able to click the Change Working Week button. This will allow you to set which days production takes place on, once you have set up your working week click OK.

Did this answer your question?