When choosing "Create Purchase Orders" for the first time in an MRP run, choose the 'Take Future Supply into Account' option
This Option is a way of preventing over ordering and carrying excess stock.
MRP is suggesting ordering something which is not due to go out to the customer for another month I.e.:- Customer order is due for 1 months time but is telling us to order it 3 weeks ago?
When choosing "Create Purchase Orders" for the first time in an MRP run, choose the 'Take Future Supply into Account' option
This Option is a way of preventing over ordering and carrying excess stock.