Initial Set Up
To use PO Authorisation it is first necessary to set the PO_AUTHORISATION flag to ‘Yes’. Follow these steps to do this:
Click on System Maintenance
Go to System Settings
Click on GENERAL System Settings
Click on Control File
In the 'Control Item' field, type in PO_AUTHORISATION and press enter
Press Ctrl+M and change the 'Value' field to Yes.
To reset the menus to include the extra options, go to File, then click Refresh Menus
Setting Authorisation Levels
To set up PO Authorisation levels:
Go to Options
Click on the System maintenance Option
Select System Settings from the list
Next, Choose PURCHASE System Settings
Click on Authorisation Levels
Now the authorisation levels can be set
By clicking on ‘supplier authorisation’ the user can make it so that a user can only authorise certain suppliers up to the limit that they have.
Using PO Authorisation
With authorisation enabled, any new PO goes into "Planning":
Clicking on "Request" and Yes on the following screen to put the PO into the "To Be Authorised" queue
Then the "Authorise" link can be clicked to authorise the PO (if the user has the correct authorisation levels)
The option to authorise or reject is then available
The PO now has the user that authorised it, but the authorisation can be removed with the "Remove" link
The soon it has been, when you come out it asks if you would like to request authorisation because it is back in "Planning"
It will also ask if you want to change the PO to Planning or Historic
While the PO is authorised, the prices cannot be changed